Building permits in the Keys

In the Keys, almost any work beyond paint and flooring needs a building permit. Which office issues it depends on the town, and because most Keys houses sit in a flood zone, extra flood rules apply that can turn a big renovation into raising the house.

A hand-drawn electrical plan for a boat lift, stamped Electrical plans reviewed and approved
A real Keys permit drawing: power for a dock boat lift, a 240-volt, 30-amp twist-lock outlet fed by #10 wire in PVC conduit. The building department stamped it approved.
A boat raised on an aluminum lift beside a concrete canal dock
A boat lift on a canal dock. The lift and the power to it both need permits.

Last checked November 2026. Rules, fees and phone numbers change. Call the building department for the house's town before you start work or count on doing it.

Who issues permits

Each city and village in the Keys runs its own building department. Everywhere else is Monroe County.

Where the house isBuilding departmentApply online
Unincorporated Monroe CountyBig Pine, Summerland, Cudjoe, Sugarloaf, Ramrod, Stock Island, Duck Key, Tavernier, Key Largo and more Key West 305-294-4641 · Marathon 305-289-2501 · Key Largo 305-453-8800 · Big Pine 305-289-2877 · Stock Island 305-295-3990Offices open 8:30 a.m. to 3 p.m. Online Permitting ServicesRegister first; paper applications aren't accepted
City of Key West 1300 White St · 305-809-3956 eTRAKiT, from the Building Department page
City of MarathonIncluding Grassy Key 305-289-5052 · inspections 305-289-4133 OpenGov portal
Islamorada 86800 Overseas Hwy · 305-664-6400 CityView portalApplications only accepted online
Key Colony Beach 600 W Ocean Dr · 305-289-1212 ext. 3 Citizenserve, from the city page
City of Layton 305-664-4667 Call city hall; we couldn't find an online portal.

Not sure which applies? Each house page on our map shows its tax area, which follows the same town lines.

What needs a permit

Florida law makes it unlawful to build, alter, repair or demolish a building without a permit unless the law says otherwise. In practice, plan on a permit for:

Almost always a permit

  • Roofing and re-roofing (Islamorada: anything over one roofing square, 100 sq ft)
  • Windows, doors, shutters and other storm protection
  • Air conditioning replacements, ductwork and fans
  • Water heater changeouts and repiping
  • Electrical wiring, lighting and service panels
  • Solar panels and batteries
  • Structural work, additions, decks and sheds
  • Fences, docks, boat lifts and davits, seawalls and pools
  • Demolition, fill, excavation and clearing land
  • Anything touching flood rules, such as work under a raised house

Usually no permit

  • Painting
  • Carpet, tile and other floor coverings
  • Normal maintenance that doesn't change a part's size, capacity or type
  • Small satellite dishes (up to one meter)
  • Roof repairs under 100 sq ft (Islamorada)

The lists above combine Islamorada's official list with the kinds of work Florida's permit law names. Other towns' lists differ in the details, so ask before you start.

Florida's $7,500 exemption, and why most Keys houses can't use it

Since July 1, 2026, Florida law lets the owner of a single-family house skip the permit for work valued under $7,500. But it doesn't apply to:

A project can't be split into smaller jobs to get under $7,500, and you still have to send the building department a written request with the contract or other proof of what the work is and what it costs. So in practice the exemption covers small cosmetic or exterior jobs on the minority of Keys houses in zone X. Each house page on our map shows its FEMA zone.

The 50% rule: when a renovation means raising the house

This is the rule that matters most when you buy an older, ground-level Keys house. If the cost of improvements or repairs reaches 50% of the market value of the building (not the land), the work counts as a "substantial improvement," and the house must be brought up to today's flood rules. For most ground-level houses that means raising the living floor to the flood level or above, or tearing down and rebuilding.

Before you buy a house you plan to renovate, ask the building department for its building value and how much work has been permitted recently. A renovation budget near half the building's value can turn into an elevation project. How floor height and flood levels work.

Space under a raised house

Enclosed space below the flood level may be used only for parking, building access and limited storage. Monroe County says limited storage does not include household furnishings, workbenches, freezers or refrigerators, and that finished space down there may lead to enforcement. The county also has a non-conversion agreement for downstairs enclosures, a promise not to turn the space into living area. If a listing shows a downstairs bedroom or apartment, ask whether it was permitted.

How to get a permit

  1. Find the right department from the table above.
  2. Hire a Florida-licensed contractor, who usually pulls the permit. Check the license with the Florida Department of Business and Professional Regulation before you sign.
  3. Or pull it yourself as an owner-builder. Florida allows this for your own house, but you must appear in person, sign the application and a disclosure statement, and take legal and financial responsibility for the work. Monroe County requires the owner-builder to be there for every inspection.
  4. Apply online with plans and documents. Florida law now requires a decision within 5 business days for a complete application on an existing single-family house when the work is under $15,000, for permits such as roofing, electrical, plumbing, mechanical, gas and structural.
  5. Record a Notice of Commencement when the job is over $5,000 (or $15,000 for replacing an air conditioning system), before the first inspection. Monroe County and Islamorada both use those thresholds.
  6. Pass the inspections and get a final. Under state law since July 1, 2026, a permit for a single-family house lasts at least a year from when it's issued; ask your department about extensions, since some pages still show older rules.

Starting work before the permit is issued usually means an "after the fact" permit with extra fees, and an inspector may make you open finished walls to check the work.

Before you buy: check the permits

Unpermitted work stays with the house. Monroe County warns that after you buy, you may be required to fix it at your own expense. Before closing:

Each house page on our map links to the house's county record, which has the parcel number the permit searches use.

Sources